Industrial Metal Pipe Cleaning And Blowing

Jun 09, 2025

Pipe Cleaning and Blowing
In accordance with the "industrial metal pipeline engineering construction and acceptance specification" (GB50235) requirements, the pipeline in the pressure test after passing, should be purged or cleaned (referred to as blowing). Blow washing method should be based on the use of pipeline requirements, transport media and the degree of dirty pipe surface to determine. Blow cleaning methods are water cleaning, chemical cleaning, oil cleaning, air blowing, steam blowing and so on. Nominal diameter greater than or equal to 600mm of liquid or gas pipeline, it is appropriate to use manual cleaning; nominal diameter of less than 600mm of liquid pipeline is appropriate to use water flushing; nominal diameter of less than 600mm of gas pipeline is appropriate to take the air blowing; steam pipeline should be steam blowing; non-thermal pipeline shall not be used for steam blowing.
I. Water cleaning
Water cleaning is water flushing. Pipeline flushing should use clean water, flushing austenitic stainless steel pipeline, the chlorine ion content in water shall not exceed 25 parts per million; flushing is recommended to use the maximum flow rate, the flow rate shall not be less than 1.5m/s; discharge water should be introduced into a reliable drainage wells or ditches, the cross-sectional area of the discharge pipe shall not be less than the cross-sectional area of the pipe to be flushed 75% of the drainage shall not be the formation of negative pressure; pipeline drainage pipe should be completely flushed; water Flushing should be carried out continuously, and the color and transparency of the water at the discharge outlet and the water at the inlet should be visually consistent as qualified; when the pipeline is not in operation for a while after being qualified for water flushing, it should be blown dry in time.

Titanium Pipeseamless titanium tubetitanium round tube

Second, chemical cleaning
When the pipeline is chemically cleaned, it must be isolated from unrelated equipments; the formula of chemical cleaning fluid must be identified and used in the production device, which has been proved to be effective and reliable; when chemically cleaned, the operators should wear special protective clothing, and according to the hazards of different cleaning fluids on the human body with goggles, gas masks and other protective gear; chemically cleaned pipeline, when it can't be put into operation in time, it should be closed or nitrogen-filled protection; chemical cleaning should be carried out in a timely manner; chemical cleaning should be carried out in a timely manner to protect the pipeline. When the pipeline qualified for chemical cleaning cannot be put into operation in time, it should be closed or filled with nitrogen for protection; the treatment and discharge of waste liquid after chemical cleaning should be in line with the provisions of environmental protection. Acid washing and alkali washing of pipelines belong to the scope of chemical cleaning.
Oil cleaning
Lubrication, sealing and control of oil pipeline, should be in the mechanical and pipeline pickling after passing the system test run before oil cleaning; oil cleaning should be carried out in the form of oil circulation, circulation process every 8 hours should be in the range of 40 ~ 70 ℃ repeatedly lift the oil temperature for 2 ~ 3 times, and should be cleaned in a timely manner or replacement of the cartridge; when the design documents or manufacturers do not require, the pipeline should be cleaned with oil filter test, the qualification standards should be consistent with the Mechanical speed ≥ 6000r/min screen specification 200 mesh or mechanical speed < 6000r/min screen specification 100 mesh, visual inspection of the screen, no hard particles and viscous matter, per cm2 range, soft debris is not more than 3; oil cleaning should be used to clean the machinery suitable for the cleaning of the oil, cleaning of qualified pipeline, effective protection measures should be taken; test run should be used before the certificate of conformity of the Working oil should be used with qualified certificate before test run.
Four, air blowing
Pipeline air blowing should be used to produce large-scale compressor device, can also use the device in the large container gas storage, intermittent blowing; blowing pressure shall not exceed the design pressure of the pipeline, the flow rate should not be less than 20m / s, blowing oil pipeline, the gas shall not contain oil; air blowing process, when the visual inspection of the exhaust smoke, should be set up in the exhaust port of the white cloth or painted white wooden target plate test, no smoke on the target plate within 5min. No rust, dust, moisture and other debris on the target board within 5min is qualified.
V. Steam blowing
Pipeline steam blowing, steam blowing for the installation of temporary piping should be installed according to the technical requirements of the steam pipeline, the installation quality should be in line with the provisions of the specification; steam pipeline should be blown with a high flow rate of steam, the flow rate should not be less than 30m/s; steam blowing should be blown according to the order of the cycle of heating-cooling-heating, it is advisable to take blowing Blowing one pipe at a time, taking turns to blow the method; to the steam turbine or design documents have provisions of the steam pipeline, steam blowing should be examined after the target piece, when the design documents are not specified, the quality should be in line with the target piece of traces φ0.6mm or less, the depth of traces <0.5mm, the number of grains 1/cm2, time 15min (both are qualified), and so on.